1. Scope of application This Installation Manual suits for the Fiber Optic Splice Closure (Hereafter abbreviated as FOSC), as the guidance of proper installation.
The scope of application is: aerial and wall-mounting. The ambient temperature ranges from -40 to 60℃.
2. Basic structure and configuration 2.1 Dimension and capacity
2.2 Main components
2.3 Main accessories and special tools
3. Necessary tools for installation 3.1 Supplementary materials (to be provided by operator)
3.2 Special tools (to be provided by operator)
3.3 Universal tools (to be provided by operator)
3.4 Splicing and testing instruments (to be provided by operator)
Notice: The above-mentioned tools and testing instruments should be provided by the operators themselves.
4. Installation flow chart 1. Open the closure 2. Determine length of fiber cable to be fixed and stripped inside FOSC 3. Strip off protective coats of fiber cable and fiber 4. Separate fiber cores and prepare work prior to fixing fiber cable 5. Fix reinforced core and fiber cable 6. Splice fibers 7. Install heat shrinkable protective sleeve and house fibers 8. Check up comprehensively 9. Assemble FOSC housing and fixing FOSC
5. The process of installing FOSC 5.1 Step One - Open the closure 5.1.1 Cleaning the locale and determine where to install the FOSC and then place fiber cables required. 5.1.2 Check whether the main components and accessories have been well prepared inside the package. 5.1.3 Open the closure ①Use the special wrench to demount all the locating bolts on the housing as well as fixing bolts at four corners and then succeed in opening closure. ② Pull the FOSC cover upwards out .installation could begin.
5.1.4 See Drawing 1 Important issues: If the weather condition is not good enough, then a tent must be pitched for waterproof and dustproof.
5.2 Step Two -Determine length of fiber cable to be fixed and stripped inside FOSC 5.2.1 Please refer to Drawing 2 for stripping length. ①. Fiber cable in 60mm length: the distance from seal fitting to fiber cable pressboard ②. Fiber cable in 1950mm length: it is used to be winded and spliced after stripping. ③. Fiber with protective coat in 1350mm length: the distance from the fixing point of fiber cable to the fixing point of FOST (fiber optic splice tray). ④. Fiber in 1600mm length: after stripping off the protective coat, it is to be winded inside the FOST after splicing with other fibers 5.2.2 See Drawing 2 Important issues:
1. Reserve enough length of fiber cable to be spliced. 2. Stripping length also could be decided by customer according to installation requirement.
5.3 Step Three – Strip off fiber protective coat of fiber cable and fiber 5.3.1 Strip off protective coat of fiber cable from the temp. locating mark with the cutter and the stripper, please refer to Drawing 2 for stripping length. Stripping length also could be decided according to installation requirement 5.3.2 See Drawing 3. Important issues: If it is difficult to strip off all the protective coat of fiber cable at one time, strip it off section by section to avoid fiber breakage. 5.4 Step Four – Separate fiber cores and prepare work prior to fixing fiber cable. 5.4.1 Wind 2 layers of insulation tape on protective coat of fiber core for protection. Meanwhile, get rid of the stuffing to separate fiber and clean them. Form a ring with the diameter of 100mm or so and fix it on the fiber temporarily by adhesive tape. 5.4.2 FOSC-X is provided with 4 inlet/outlet ports ,the inlet/outlet ports cloud be decided to according to diameter of fiber cables to be actully installed .then the corresponding number of ports plugs should be take out. 5.4.3 This FOSC is stuitable for the following diameters of fiber cables respectivly Port A :stuitable for fiber cable with max :diameter 18MM Port B :stuitable for fiber cable with max :diameter 6MM 5.4.4 The corresponding inlet/outlet ports are to be selected according to fiber cables actully installed .when the diameter of fiber cable is smaller then that of the inlet/outlet ports .then the seal tape shuold be used enlarge the diameter of fiber cable.of which the perimeter could be measured by the corresponding measuring paper. 5.4.5 Reserve reinforced core in 35mm length and cut off the unnecessary ones. 5.4.6 See Drawing 4 Important Issues: 1.Before the seal tape is used for enlarging the fiber cable diameter,it shuold be scratched and to be cleaned with abrasive cloth ethyl alcohol. 2.Cut off reinforced core with a special cutting plier.
5.5 Step Five - Fix reinforced core and fiber cable 5.5.1 UP finishing the above steps ,then demount port plugs,pressboard and fixing out of reinforced core.Make sure whether the fiber cable stripped fits in with the fixing ports or not.if not adjustment should be done in time .Otherwise it will affect installation quality. 5.5.2 tighten fiber cable pressboart.diameter of fiber cable is small.then enlarge it with insulation tape. 5.5.3 tighten out of reinforced core with the special wrench (plastic) and then retighten it with metal wrench(the metal wrench shuold be provided operator) 5.5.4 See Drawing 5 Important Issues: 1.fixing out of einforced core should be tightened 2.while heating.heat shrinkable fix tube shuold shrik evenly .and there should be no bubbles .pores and other defects inside the tube. 5.6 Step Six - Splice fibers 5.6.1 Follow user manual of fusion splicing machine to splice fiber. Important issue: pay attention to the twist and bend of fiber.
5.7 Step Seven -Install heat shrinkable protective sleeve and house fibers 5.7.1 When having completed splicing the fibers, the first fiber ring should be housed on the farthest side of FOST, the remaining fiber should be winded, forming a ring with diameter not less than 80mm. then put it into FOST (Fiber Optic Splice Tray) together with heat shrinkable protective sleeve.( Firstly fix heat shrinkable protective sleeve into the slot, then enlarge the diameter of fiber ring properly.) Important issue :pay attention to the twist and bend of fiber.
5.8 Step Eight - Check up comprehensively To ensure the technical requirements, the following instructions must be followed: 5.8.1 The fibers in the FOST are spliced and installed orderly. The curved diameter of fiber meets with the technical requirements. 5.8.2 The inlet/outlet ports without fiber cables installed must be blocked up with the port plugs. 5.8.3 Fibers with protective coat are fixed with nylon ta the entrance of FOST. 5.8.4 The inlet/outlet ports without fiber cables installed must be blocked up with the port plugs.
5.8.5Control the amount of seal tape within a proper range. 5.8.6 Seal fitting is installed neatly and smoothly. If not, level it up with seal tape. Important issue : If any problems occur, they should be solved right away
5.9 Step Nine – Assemble FOSC housing 5.9.1 Put the FOSC cover on the FOSC bottom directly. 5.9.2 Insert locating bolt of FOSC and tighten it with the special wrench. Important issues: cleaning the housing and pay attention to the above sequence.
6. Fiber Optic Splice Closures (FOSC) inspecting and testing items
|